ZESCO LIMITED 2016 PROCUREMENT PLAN FOR WORKS, GOODS AND NON-CONSULTING SERVICES | Download |
ZESCO LIMITED 2016 PROCUREMENT PLAN FOR CONSULTING SERVICES | Download |
Kitwe Central Switching Station is a 95MVA, 330/220/11kV Substation established with the purpose of supplying power to the mines through Copperbelt Energy Corporation (CEC) and Copperbelt Distribution Customers. The substation feeds CEC and Copperbelt Distribution Customers
Location : Kitwe
Capacity :95 MVA
Kabwe Step Down substation is a 181MVA 330/88/66/11kV Substation, established with the purpose supplying power to Kabwe loads and facilitating the supply of power to the Copperbelt, Northern, Luapula, Eastern and Muchinga Provinces. The substation feeds Copperbelt, Northern, Luapula, Eastern and Muchinga Provinces.
Location : Kabwe
Capacity :181 MVA
Luano substation is a 990MVA, 330/220/11kV substation, established with the purpose of supplying power to Copperbelt and North-Western Loads The substation feeds to Copperbelt and North-Western Loads
Location : ,Chingola
Capacity :900 MVA
Chambishi East substation is a 240MVA 330/66/11 kV substation, established with the purpose supplying power to Copperbelt Loads The substation feeds Copperbelt Loads
Location : Kitwe
Capacity :240 MVA
Kansanshi substation is a 330/33/11k, 450MVA substation, established with the purpose of supplying power to Kansanshi Mine and North-Western Province Customers The substation feeds Kansanshi Mine and North-Western Customers.
Location : Solwezi
Capacity :450 MVA
Msoro Substation is a 330/66/11kV, 90MVA Substation established with the purpose of supplying power to Eastern Province Districts The substation feeds Eastern Province Districts.
Location : Mambwe
Capacity :90 MVA
North-Western substations 132/33/11 substations of various capacities, established in with the purpose of supplying power to North-Western Districts of Kabompo, Mumbezhi, Zambezi, Chavuma, Mwinilunga and Mufumbwe. The substations feed Kabompo, Mumbezhi, zambezi, Chavuma, Mwinilunga and Mufumbwe Districts
Location : KABOMPO, MUMBEZHI, ZAMBEZI, CHAVUMA
Capacity :132/33KV
Sesheke Substation is a 220/66/11kV 20MVA & 10MVA substation, established with the purpose of supplying power to towns in Western Province and facilitating power exports/imports to Namibia. The substation feeds Western Province and facilitates power exchanges between Zambia and Namibia.
Location : Sesheke
Capacity :30 MVA
Mukuni substation is 330/220kVA, 500MVA substation, established with the purpose of facilitating the evacuation of power to the subregion and the main Grid The substation feeds power to the Main Grid.
Location : Livingstone
Capacity :500 MVA
Muzuma substation is a 330/132/88/33kV, 120MVA substation, established with the purpose of evacuating power from Maamba Collieries Power Plant and supplying power to Choma, Kalomo and Namwala Districts and to the main Grid. The substation feeds power to the National Grid either Northwards to Kafue Town Substation and Southwards to Mukuni Substation and to Choma, Kalomo and Namwala Districts.
Location : Choma
Capacity :120 MVA
Leopards Hill substation is a 330/132/34.5kV and 330/88/11kV, 730MVA substation, established with the purpose of receiving power from Kafue Gorge and Kariba North Power Stations and redistributing this power to various parts of the Country through the Main grid. The substation is strategic in the Zambia Power System. The substation feeds Lusaka Loads and the National Grid.
Location : Lusaka
Capacity :730 MVA
Roma substation is a 132/33/11kV, 126MVA substation, established with the purpose of supply power in Lusaka Loads. The substation feeds Lusaka Loads
Location : Lusaka
Capacity :126 MVA
Lusaka West substation is a 330/132/33kV, 375MVA Substation established in with the purpose of supplying power to Lusaka Loads. The substation feeds Lusaka Loads.
Location : Lusaka
Capacity :375 MVA
Water Works is a 132/33/11 kV, 270MVA substation, established in with the purpose of supply power to Lusaka Loads. The substation feeds Lusaka Loads
Location : Lusaka
Capacity :270 MVA
Kafue Town substation is a 330/88kV, 375MVA Substation, established in with the purpose of supplying power to Kafue Town, Nampundwe and as an alternative supply to Leopards Hill from Kafue Gorge Power Station. The substation feeds Kafue Town and the Main Grid through Leopards Hill Substation.
Location : Lusaka
Capacity :375 MVA
The Nations Control Centre (NCC) main functions are to forecast and manage the flow of power and balance supply and demand in real time, intervening when needed. These functions ensure electricity is provided across the ZESCO network in a way that is as timely, reliable and stable. NCC Controllers, who work 24/7, ensure electricity is moved around the country from where it is generated to where its needed.
Location : Lusaka